Free Adobe AD0-E903 Questions
-
-
Page: 1/14
Total 70 Questions
Question No 1
An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes. In which project area does this information reside?
Question No 2
The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed. Which task settings should be configured to meet these requirements?
Question No 3
What item, when shared with a user, can never give that user inherited permission to a project?
Question No 4
What parent object can have child objects?
Question No 5
Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday. Why may this be the case?
-
Page: 1/14
Total 70 Questions
-